Bonn
University of Bonn – New Rotation Building
The four-winged new building surrounds a central atrium and combines laboratory, office, seminar and lecture hall spaces. The building was constructed using a combination of conventional construction methods and modular laboratory structures. This modular approach enabled precise, weather-independent fabrication and shortened construction times. At the same time, the building is designed to accommodate changing user requirements, allowing future modifications to be made with minimal effort.
wpw was responsible for Commissioning Management in accordance with VDI 6039, including the commissioning plan, cross-trade functional tests (fire scenario, black-building test and room functions), measurements and documentation.
In addition, wpw is responsible for Technical Monitoring in accordance with VDI 6041 and AMEV, including the preparation of regular monitoring reports on the building’s technical systems and recommendations for optimisation.
| Client | Construction and Real Estate Management NRW, Cologne Branch |
| Client | Cadolto Modulbau GmbH, Cadolzburg |
| Services Provided | Commissioning Management, Technical Monitoring |
| Industry | Educational Construction |